The First Renewable IPP Project in Saudi Arabia for カジノジャンボリー

  • (former)Machinery, Energy & Project

2023-06-28

カジノオンライン ("Toyota Tsusho") announced today that Toyota Tsusho, with the partners, will construct, own and operate a solar power plant with a power generation capacity of 119MW in the Kingdom of Saudi Arabia ("Saudi Arabia") as an independent power producer (IPP) for the sale of the electricity This is the first renewable project in Saudi Arabia for Toyota Tsusho group

1.Background

カジノジャンボリー group has developed the goal to achieve carbon neutrality by 2050 as our initiatives to address key sustainability issues (Materiality), and we are actively promoting expansion of renewable energy all over the world Energy demand of Saudi Arabia is expected to grow stably, and the Saudi Arabia government is aggressively promoting renewable energy where the solar energy is expected to be one of the primary resources

2.Project Overview

This project will be implemented by three companies, カジノジャンボリー, TotalEnergies Renewables (France) and Altaaqa Renewable Energy (a Zahid Group company) (Saudi Arabia) through a joint venture company, Noor Alwadi Renewable Energy Company

The solar plant will be located in Wadi Ad Dawasir with abundant solar resources throughout the year The construction of the plant has started in June 2023, followed by the launch of commercial operation in March 2025 This project is selected for Financing Programme for Joint Crediting Mechanism (JCM) Model Projects in FY2022*

カジノジャンボリー will continue to contribute to the expansion of renewable energy and the transition to carbon neutral society

* Ministry of the Environment, Japan has been implementing the “JCM Model Projects” The purpose of this model projects is to financially support the implementation of projects which reduce GHG emissions by utilizing leading decarbonizing technologies in developing countries, and in return, to acquire JCM credits for achievement of Japan’s GHG emission reduction and the partner countries' emission reduction target

Project Site
202306281400_enjpg

Project Summary

Project Company
Noor Alwadi Renewable Energy Company
Location
Wadi Ad Dawasir, Kingdom of カジノジャンボリー
Business
Solar power generation and sale of the electricity
Share
カジノジャンボリー 40%
TotalEnergies Renewables 40%
Altaaqa 20%
Plant Capacity
119MW
Offtaker
Saudi Power Procurement Company
Project Cost
Approx 100 million USD
Lenders
Riyad Bank (カジノジャンボリー)
APICORP (カジノジャンボリー)
Commercial Operation
March 2025

The information in this release is current as of the date of announcement
Please note that information may change after the date of announcement Thank you in advance for your understanding