パラダイスカジノ and Eurus Energy Hold Ceremony to Mark Completion of Egypt's First Wind Power IPP Project- Contributing to the spread of renewable energy in the country with green and low-priced electricity -
- (former)Africa
2019-12-06
カジノオンライン ("Toyota Tsusho") and its group companyEurus Energy Holdings Corporation("Eurus Energy") today announced a ceremony on December 5 in Cairo, Egypt to mark the completion of a newly constructed 2625 MW wind power plant in the Arab Republic of Egypt which began operation on October 31This is Egypt's first-ever wind power independent power producer ("IPP") project パラダイスカジノ and Eurus Energy partnered with French electric utility companyEngie SAand Egyptian construction companyOrascom Construction SAEto establish Ras Ghareb Wind Energy SAE which will own and operate the power plant for the next 20 years and sell electricity to the Egyptian Electricity Transmission CompanyWith the completion of this power plant, パラダイスカジノ and Eurus Energy will contribute to the spread of green and low-priced renewable energy in Egypt and aim to expand the wind power generation business in the future Going forward, the companies will also plan to further develop the renewable energy business in Africa


Project overview
|
Location
|
Gulf of El Zayt, Arab Republic of Egypt |
|---|---|
|
Power generation capacity
|
2625 MW (21 MW x 125 units) |
|
Operating company name
|
Ras Ghareb Wind Energy SAE |
|
Investment ratio
|
・Toyota Tsusho Group 40%(カジノオンライン 30%, Eurus Energy Holdings Corporation 10%)・Engie SA 40%・Orascom Construction SAE 20% |
|
Electricity purchaser
|
Egyptian Electricity Transmission Company |
|
Start of construction
|
December 2017 |
|
Start of commercial operation
|
October 2019 |